Page 14 - ADG - Continuous Energy with Reliable Collaboration
P. 14
TECHNICAL PROCEDURE
• An exploration is performed in the customer’s facility
and a location for the field of LNG tanks is selected as
per the contract made with the customer.
• LNG field project, which includes construction activities
and other requirements, is prepared.
• When the construction of the tank site is completed,
the LNG tank and it’s equipment is brought up to the
site.
• Installation is performed after making the necessary
electrical and mechanical connections.
• The internal installation for natural gas is approved by
the authorized body certified by EPDK (Energy Market
Regulatory Authority).
• Users are given practical training on LNG and the LNG
system and the system is commissioned after filling it
for the first time with LNG.